A letter titled Notice of Right to Lien can arrive in the mail a few weeks into a remodel, often from a company you have never heard of. Nevada law requires it. This page explains what it means, what it does not mean, and what to do with it.
What the notice is
Under NRS 108.245, every lien claimant other than someone who performs only labor must, at any time after first delivering material or performing work, deliver to the owner, in person or by certified mail, a notice of right to lien in the statutory form. The form names you, describes the materials, equipment or work, identifies your property and the contractor they are working under, and states:
"This is not a notice that the undersigned has not been or does not expect to be paid, but a notice required by law that the undersigned may, at a future date, record a notice of lien as provided by law against the property if the undersigned is not paid."
A subcontractor or supplier who sends you the notice must also send a copy to the prime contractor (NRS 108.245(1)).
Why it matters to the sender
- No notice, no lien for materials, equipment or non-labor work: "No lien for materials or equipment furnished or for work or services performed, except labor, may be perfected or enforced ... unless the notice has been given" (NRS 108.245(3)).
- The 31-day lookback. A claimant who gives the notice has lien rights for what it furnished in the 31 days before the notice, and for everything after until completion (NRS 108.245(6)).
- Not a lien itself. The notice "does not constitute a lien or give actual or constructive notice of a lien for any purpose" (NRS 108.245(2)).
Who does not send it
Your prime contractor, anyone else who contracts directly with you, and anyone who sells materials directly to you are not required to send the notice (NRS 108.245(5)). Laborers are also excluded.
What to do when you get one
- Keep it in your job file. It tells you who could lien your home.
- Match it to the contractor's list. A general building contractor must give you the names, license numbers and contact details of all subcontractors and of suppliers furnishing $500 or more of material (NRS 624.600). Ask about any sender who is not on it.
- Check licenses. Search subcontractors on NSCB License Search. NSCB's Home Improvement Bill of Rights suggests listing all subcontractors, checking their licenses, and getting lien releases from all subcontractors and suppliers.
- Collect releases tied to payments. Before each payment to your contractor, ask for a conditional waiver from this sender covering the amount being paid; after it clears, ask for the unconditional waiver. Only the statutory forms in NRS 108.2457 are enforceable.
- Consider joint checks. A two-party check payable to the contractor and the supplier counts as payment to the supplier once endorsed and cleared, up to the amounts the statute describes (NRS 108.2457(3)).
- Send them your notice of completion. If you record a notice of completion, you must mail a copy within 10 days to every claimant who sent you a notice of right to lien, or the notice is ineffective as to them (NRS 108.228).
The second warning: notice of intent to lien
On a residential job, before recording a lien, a claimant (except a laborer) must serve the owner and the reputed prime contractor with a 15-day notice of intent to lien, by personal delivery or certified mail (NRS 108.226(6)). This one means someone says they are owed money. Call your contractor and the sender the day it arrives, and do not release another payment until you know how the debt will be paid.
If the sender wasn't paid
Your options include paying the sender directly by joint check against the next draw, withholding the disputed amount from the contractor under the contract's terms, or, if a lien is recorded, bonding around it at 1.5 times the lien amount (NRS 108.2415). A licensed contractor's failure to pay for materials or services after receiving money for them is cause for discipline (NRS 624.3012), and you can file a complaint with NSCB.
Related pages
Sources
- NRS 108.245 Notice of right to lien
- NRS 108.226 Notice of intent to lien
- NRS 108.228 Notice of completion
- NRS 108.2415 Surety bond to release lien
- NRS 108.2457 Waiver and release
- NRS 624.600 Disclosure of subcontractors and suppliers
- NRS 624.3012 Failure to pay for materials or services
- NSCB: Home Improvement Bill of Rights
Frequently Asked Questions
Does a notice of right to lien mean my contractor isn't paying?
No. The statutory form says it is 'not a notice that the undersigned has not been or does not expect to be paid, but a notice required by law' (NRS 108.245(1)). Subcontractors and suppliers send it to keep their lien rights.
Does my general contractor have to send me a notice of right to lien?
No. A prime contractor or anyone who contracts directly with the owner, or sells materials directly to the owner, is not required to give the notice (NRS 108.245(5)).
What is the difference between a notice of right to lien and a notice of intent to lien?
The notice of right to lien (NRS 108.245) goes out early in the job to preserve rights. The 15-day notice of intent to lien (NRS 108.226(6)) must be served on the owner and prime contractor of a residential job at least 15 days before a claimant records a lien, so it signals an actual payment problem.