A backyard pool is one of the largest contracts a Nevada homeowner signs, and the Legislature gave it its own set of rules. Pool and spa contracts have the strictest consequence in chapter 624: a contract that doesn't follow the rules is void and unenforceable against you (NRS 624.940(5)). This page lists what the contract must contain and how payments must work.
Who must be licensed
"Work concerning a residential pool or spa" means design, construction, repair, maintenance, restoration, alteration or improvement of a residential pool or spa, including equipment replacement, and consultation or supervision of that work, when done for a fee (NRS 624.915). The scope runs from layout and excavation through steel, gunite, tile, coping, plaster, piping, filters, decks and packaged heaters.
No one may do, offer or advertise that work for a fee without a license or other state authorization covering it (NRS 624.920). The pool subclassification is A-10, with A-10a Residential Pools, A-10c Repair, A-10d Fiberglass, A-10e Maintenance and Repair, and A-10f water and gas lines for residential pools (NAC 624.150). Solar pool heating is C-37d (NAC 624.540).
What the contract must contain
For a contract over $1,000 with the owner of a single-family residence, NRS 624.940(2) requires in writing:
- Contractor's name, business address and license number
- Owner's name and mailing address, and the property address or legal description
- Date signed and estimated completion date
- Description of the work and the total price including taxes
- Down payment of no more than $1,000 or 10 percent of the price, whichever is less
- A statement that you received the subcontractor, supplier and lien disclosures required by NRS 624.600
- A statement that extra work and changes must be in a written change order you sign, stating the scope and price
- A plan and scale drawing showing shape, size, dimensions and specifications, with materials and equipment
- A payment schedule in dollars and cents by stage, never more than 100 percent of the value of work performed
- If a salesperson's commission comes out of the price, a statement that it is paid pro rata
NSCB's regulation adds, in at least 10-point bold type (NAC 624.6958):
- A schedule of payments meeting NAC 624.6964
- The contractor's agreement to pay each subcontractor and supplier promptly and in full after each stage
- A statement that the contractor will give you an unconditional lien release for each paid stage before requesting further payment
The contract must also have spaces for your initials, a notice near the signatures that you may contact the Board and may request a payment and performance bond, a legible copy of everything you sign, and a signed receipt for any money paid (NRS 624.940(3)-(4)).
The payment schedule
NAC 624.6964 sets the rules:
- Each payment references the specific work, materials and equipment it covers.
- No stage may be scheduled to take more than 30 days, unless delayed by an act of God or you agree in writing.
- Payment for a stage is not due until that stage is complete.
- The contractor may not receive more than 100 percent of the contracted amount for any stage.
- Final payment may be required after plastering and the building department's final inspection, unless contracted equipment, decking or fencing is unfinished.
These schedule rules do not apply if the contractor furnishes a payment and performance bond for the full contract, or if the contract calls for full payment only on satisfactory completion of the whole project.
Duties once you sign
Under NRS 624.935 and NAC 624.6966:
- A contractor who takes the down payment must start within 30 days after permits issue, unless you agree in writing to longer.
- It must work diligently and may not stop work for any 30-day period.
- After each satisfactory payment, it must give you a full and unconditional lien release for that portion before any further payment, unless a payment and performance bond or joint control is in place.
- It must apply for all permits in a timely manner, and the contract must include a written statement of your rights under NRS 624.900 to 624.965.
Consumer bond
Pool contractors post a consumer protection bond of $10,000 to $400,000 on top of the license bond, for the benefit of homeowners damaged by failure to perform or to remove liens (NRS 624.276). Repeat violators can be required to post performance and payment bonds of at least 50 percent of the contract (NRS 624.270(7)-(8)). See contractor bond requirements.
Before you sign
NSCB's Guide to Contracting for a Pool or Spa recommends:
- Confirm the contractor and every subcontractor are licensed.
- Get at least three written bids and be cautious of deals that sound too good to be true.
- Ask for references, including financial references.
- Approve all completed plans before work starts.
- Never pay in full up front.
- Do not pull permits in your own name.
On a pool, barrier and drainage questions go to your building department. The City of Las Vegas notes that pool barriers are required even where the pool itself is exempt from a permit (When Do I Need a Permit?).
Help with a dispute
NSCB's Ombudsman for Residential Pools and Spas helps owners and contractors understand their rights under these sections (NRS 624.105). Breaking the pool contract rules is cause for discipline (NRS 624.3016(5)(a)). See filing an NSCB complaint.
Related pages
- Nevada residential contract requirements
- Nevada mechanics' lien law
- Nevada Residential Recovery Fund
Sources
- NRS 624.900 to 624.965 Residential pools and spas
- NRS 624.105 Ombudsman for Residential Pools and Spas
- NRS 624.276 Pool and spa consumer bond
- NAC 624.6958, 624.6964, 624.6966 Pool contract regulations
- NAC 624.150 Classification A-10
- NSCB: Guide to Contracting for a Pool or Spa
- City of Las Vegas: When Do I Need a Permit?
Frequently Asked Questions
What license does a pool builder need in Nevada?
Residential pool construction falls under subclassification A-10 (Commercial and Residential Pools), including A-10a Residential Pools, A-10d Fiberglass and A-10e Maintenance and Repair (NAC 624.150). NRS 624.920 bars anyone from doing or offering pool or spa work for a fee without a license that authorizes it.
When can a Nevada pool contractor demand final payment?
After plastering is complete and the local building department's final inspection is done, unless equipment, decking or fencing required by the contract is still unfinished (NRS 624.935(6); NAC 624.6964(6)).
Who can help me with a pool contract dispute in Nevada?
NSCB has an Ombudsman for Residential Pools and Spas, whose job is to help owners and contractors understand their rights and duties under NRS 624.900 to 624.965 (NRS 624.105).
Does a pool contractor have to pull the permit?
Yes. The contractor must apply for and obtain all necessary permits (NRS 624.940(6)), and NSCB's pool guide tells owners not to pull permits in their own name.