Nevada has a statute that spells out what goes into a contract for work on an owner-occupied home. NRS 624.970 came from Assembly Bill 39 (2023) and applies to contracts signed on or after October 1, 2023 (NSCB Bonds page). Use this page as a checklist when a bid turns into a contract.
Which contracts it covers
The section applies to a contract between a licensed residential contractor and the owner of a single-family residence who occupies it, for "any construction, remodeling, repair or improvement" to a completed home (NRS 624.970(7)). It does not cover:
- Residential solar photovoltaic work, which has its own rules in NRS 624.875. See solar contract rules.
- Residential pools and spas, covered by NRS 624.940. See pool and spa contract rules.
"Single-family residence" includes a detached house, a condominium or townhouse unit, or a duplex unit that is the owner's residence, and excludes mobile and manufactured homes and rentals to non-family (NRS 624.455).
What the contract must contain
NRS 624.970(2) lists the required written terms:
- Contractor name, address, license number and monetary limit.
- Owner name and mailing address, and the property address or legal description.
- Date the contract is signed.
- Estimated completion date for all the work.
- Description of the work.
- Total price for all the work, including all applicable taxes.
- Down payment amount, capped at $1,000 or 10 percent of the contract price, whichever is less.
- A statement that the contractor gave you the Recovery Fund notice and the lien informational form required by NRS 624.520 and NRS 624.600.
- A statement that changes in scope or price must be agreed in writing as a change order. A change order is not enforceable against you unless it sets out all changes in scope and price and you accept it.
- For a project of new work, a plan and scale drawing with specifications, plus a description of work, materials, equipment and price. Repair-only jobs are excused.
- A payment schedule in dollars and cents tied to stages of construction.
- If a salesperson's commission comes out of the price, a statement that it is paid pro rata with the payment schedule.
What counts as "new work"
NSCB's regulation reads "project of new work" broadly. It includes work that needs a building permit; moves, adds or removes interior walls; changes ductwork, plumbing or electrical systems; kitchen or bathroom remodels with cabinets; landscaping with plants, walkways, patios or walls; added square footage; or any job where the contractor showed you a plan (NAC 624.012). "Repair" includes replacing or maintaining installed equipment such as HVAC units, plumbing fixtures, chimneys and garage doors (NAC 624.013).
The deposit cap
The $1,000-or-10-percent cap does not apply if the contractor has filed a $100,000 bond with NSCB "solely for the protection of consumers," or was relieved of the license bond under NRS 624.270(5) (NRS 624.970(2)(g)). NSCB's Consumer Checklist says you can check a contractor's bond status on its website.
Examples under the cap:
| Contract price | 10 percent | Maximum deposit |
|---|---|---|
| $6,000 | $600 | $600 |
| $10,000 | $1,000 | $1,000 |
| $45,000 | $4,500 | $1,000 |
Payments can't run ahead of the work
The payment schedule "must not provide for the residential contractor to receive, nor may the residential contractor actually receive, payments in excess of 100 percent of the value of the work performed on the project at any time," excluding finance charges and the down payment (NRS 624.970(2)(k)). The rule is lifted only when the contractor furnishes a payment and performance bond covering the whole contract, with the cost in the price.
Notices, initials and copies
NRS 624.970(3) and (4) also require:
- A way for you to initial provisions to show you read and understood them.
- A notice next to the signatures that you may contact the Board for help understanding the contract, request a payment and performance bond, contact an attorney, and ask for a contract in the language it was explained in.
- A legible copy of everything you signed and a signed receipt for any money you paid, at signing.
- Contract text in at least 10-point bold type. Delivery may be electronic.
The contractor gets the permits
"The residential contractor shall apply for and obtain all necessary permits" (NRS 624.970(6)). This matters to you: an owner who pulls the building permit is ineligible for the Residential Recovery Fund (NRS 624.510(2)(d)).
If the contract breaks the rules
- A contract missing required terms may be modified by the owner to bring it into compliance, and a reasonable modification is enforceable against the contractor (NRS 624.970(1)(a)).
- An oversized deposit clause is voidable by the owner (NRS 624.970(1)(b)).
- Any clause that waives your rights under chapter 624 is void (NRS 624.970(5)).
- Breaking the contract rules in NRS 624.970 or its regulations is cause for discipline (NRS 624.3016).
NSCB publishes a one-page AB 39 contract checklist you can take to the kitchen table.
Other terms to ask for
These are not required by NRS 624.970, but NSCB's Home Improvement Bill of Rights lists them as items to look for: one price for all labor and materials, start and completion dates, an agreement that the contractor will get the permits, notices about liens and the Recovery Fund, and a notice of the contractor's general liability insurance carrier.
Related pages
- Nevada mechanics' lien law
- Door-to-door sales: 3-day right to cancel
- Nevada contractor monetary limits
- Hiring checklist
Sources
- NRS 624.970 Residential improvement contracts
- NRS 624.455 Single-family residence defined
- NRS 624.510 Recovery Fund eligibility
- NRS 624.520 and 624.600 Required notices
- NAC 624.012 and 624.013
- NSCB: Bonds (AB 39)
- NSCB: Consumer Checklist
- NSCB: Home Improvement Bill of Rights
Frequently Asked Questions
How much of a deposit can a Nevada contractor take?
For work on an owner-occupied single-family home, the initial down payment may not exceed $1,000 or 10 percent of the contract price, whichever is less (NRS 624.970(2)(g)). The cap does not apply if the contractor has filed a $100,000 consumer protection bond with NSCB or was relieved of the license bond. A deposit clause that breaks the cap is voidable by the owner (NRS 624.970(1)(b)).
Can a Nevada contractor bill ahead of the work?
No. The payment schedule must show each payment in dollars and cents and may not let the contractor receive more than 100 percent of the value of work performed at any time, apart from the down payment and finance charges (NRS 624.970(2)(k)). The rule does not apply when the contractor furnishes a payment and performance bond whose cost is in the price.
Are verbal change orders binding in Nevada?
A change order is not enforceable against the owner unless it sets out all changes in scope and price and the owner accepts it (NRS 624.970(2)(i)).
Who pulls the permit under a Nevada residential contract?
The contractor. NRS 624.970(6) says the residential contractor shall apply for and obtain all necessary permits.